The UAB “Gerbūvio projektai” team is pleased to share progress from the reconstruction of the A14 Vilnius–Utena main highway, in the section from km 21.5 to km 28.4. We are delivering this project in cooperation with our client, AB “Hisk”.
Completed Works to Date
- Installation of concrete road and lawn curbs – 2,181 m
- Installation of granite road curbs – 1,609 m
- Construction of paver surfaces (grey, red, and tactile paving for accessibility) with a 15 cm dolomite base layer – 1,560 m²
- Construction of the roundabout structure in accordance with the design documentation (base preparation, leveling layer, crushed stone base, concrete elements with embedded metal parts) – 240 m²
- Installation of concrete drainage channels within the roundabout – 64.5 m
- Installation of split granite within the roundabout – 230 m²
Every meter and every square meter completed is another step toward a safer, more convenient, and more visually appealing road.
Work continues—next, we’ll move forward with the upcoming reconstruction stages and share new updates from the site. We invite partners, colleagues, and everyone interested in infrastructure development to connect, collaborate, and follow our projects.